PUPILS at Chippenham's Abbeyfield School could finally have their long-awaited playing fields when they start school in the autumn.

Headteacher Trish Shubrook said she was confident the comprehensive school, which opened in its present premises last September, would have its playing fields ready for sporting action when the new term starts on September 2.

But pupils at the school will have to travel to Bath University for their sports day on Tuesday, because the facilities are not up to scratch yet.

Mrs Shubrook, however, remained positive the 180 children's sporting education had not suffered because of the playing fields setback.

"We have been using our hard courts for PE and our indoor facilities which are excellent," she said.

"It has been an opportunity to do other games indoors. Tennis, netball and five-a-side football have gone ahead using the hard surface."

The playing fields were due to be ready a month ago, but the school was told more work was needed.

Mrs Shubrook said she had been told there was too much subsoil so stones were rising to the surface, and the pitches could not be used.

"Remedial work is now being done and we have been told the pitches will be usable by September. We are keeping our fingers crossed that is the case," she said.

"It has been a disappointment and it is very frustrating for us but the contractor is working very hard to get it sorted out."

The school was built as part of a private finance deal. The White Horse Partnership, which includes Group 4, is responsible for the maintenance and upkeep of the school.

Parents have raised concerns about the lack of playing fields, and have been assured by Mrs Shubrook that the children have been doing PE despite the current limitations.

In a letter to parents, she said: "A number of parents have contacted me to express their concern.

"I share their feelings of disappointment and frustration and want to reassure you that the governors and I are doing everything we can to improve the current situation."